2 – 3 Years
- Office and storage facilities are relocated from Synergy site to Pumpkin Patch
- Drilling of new wells on Pumpkin Patch and LCWA site begins
- Existing office structure relocated and repurposed for use as a Visitor’s Center
- Visitor Center parking lot on Synergy site constructed
- Perimeter trail completed
- Improvements to entrance road to Synergy site off of 2nd Street completed
- Northern 76 acres of Synergy site conveyed to LCWA, with Synergy retaining rights to sell Mitigation Bank credits
- 95% of all above-ground pipelines and 100% of all tanks to be removed from Synergy and City sites